Geothermal Well Drilling Initiative – Construction Update – 3/8/19
Week of 03/11/19 – 03/15/19:
Parking Lot Test Well #1
- Relocation of Rygan stockpile to storage area.
- Relocation of the temporary toilet to Parking Test Well #3.
- Relocation of fence to Parking Test Well #3 and return the parking lot to BU.
Alley Test Well #2
- Demobilizing frac tanks and roll-off container.
- Removal of stockpiled spoils/soils.
- Backfill and patch alley.
- Relocation of fence to the storage area in the alley and return the alley parking spaces to BU.
- Construction equipment will periodically enter/exit the alley from Granby Street. A loader and trailer will be within the logistics area to remove materials.
Park Test Well #3
- Mobilizing of temporary fence.
- Relocation of park benches and trash receptacle to the storage area in the alley.
- Lot to be surveyed and pre-excavated.
Week of 03/18/19 – 03/22/19
Alley Test Well #2
- Construction equipment will periodically enter the alley to access the storage area.
Park Test Well #3
- Mobilizing drilling equipment.
- Drilling, set casing, and mobilizing new drill rod.
- Construction equipment will periodically access the park from Granby Street. A water truck will periodically back out of the TW-3 site to fill up at the hydrant located at the corner of Granby St. and Bay State Rd.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!