Myles Standish Hall – Construction Update – 6/28/18

For 6/30/18 to 7/6/18:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
On-site Construction
Saturday Work – 6/30/18 – 7 am to 5 pm
- Clean up and load out
- Interior work – Myles
- Annex interior framing and MEP roughs
- Annex exterior façade work
No work Wednesday, 7/4/18 – Holiday
Myles – 7 am to 6 pm
Load Out
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpsters with ongoing daily dumpster swaps
Site
- Myles
- Bay State Road – Continue sidewalk demo, underground, and start cut and caps in Bay State Road
- Bay State Road & Beacon Street
- Continue installation of pavers and landscape
Annex – 7 am to 6 pm
Load Out
- Load out Bay State Road and Beacon Street to dumpsters with ongoing daily dumpster swaps
Roof
- Masonry restoration
- Roof terminations, flashings, and masonry
Masonry Restoration
- Beacon Street, Raleigh Street, & Bay State Road – Continue with façade restoration