Myles Standish Hall – Construction Update – 6/28/18

Myles Standish Hall - Construction Update - 6/28/18 Myles Standish Hall - Construction Update - 6/28/18

For 6/30/18 to 7/6/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

On-site Construction

Saturday Work – 6/30/18 – 7 am to 5 pm

  • Clean up and load out
  • Interior work – Myles
  • Annex interior framing and MEP roughs
  • Annex exterior façade work

No work Wednesday, 7/4/18 – Holiday

Myles – 7 am to 6 pm

Load Out

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpsters with ongoing daily dumpster swaps

Site

  • Myles
    • Bay State Road – Continue sidewalk demo, underground, and start cut and caps in Bay State Road
  •  Bay State Road & Beacon Street
    • Continue installation of pavers and landscape

Annex – 7 am to 6 pm

Load Out

  • Load out Bay State Road and Beacon Street to dumpsters with ongoing daily dumpster swaps

  Roof

  • Masonry restoration
  • Roof terminations, flashings, and masonry

 Masonry Restoration

  • Beacon Street, Raleigh Street, & Bay State Road – Continue with façade restoration