Myles Standish Hall – Construction Update – 5/31/18

Myles Standish Hall - Construction Update - 5/31/18 myles 1

For 6/2/18 to 6/11/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

On-site Construction

Saturday Work – 6/2/18 – 7 am to 5 pm

  • Clean up and load out
  • Interior work – Myles
  • Annex interior demo and load out
  • Annex exterior façade work

Myles – 7 am to 6 pm

Demolition / Load Out

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpsters with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demo at Beacon Street and Bay State Road
  • Restoration of façade at hoist location

Roof (Exterior)

  •  MEP insulation

Site

  • Myles
    • Continue sidewalk and underground demo
  •  Point Park
    • Continue installation of pavers and landscape

Annex – 7 am to 6 pm

Demolition / Load Out

  • Load out Bay State Road and Raleigh Street with chute to dumpsters with ongoing daily dumpster swaps

Roof

  • Masonry restoration
  • Roof terminations and flashings

Masonry Restoration

  • Beacon Street & Raleigh Street – Start façade restoration