Myles Standish Hall – Construction Activity – For 4/21/18 to 4/27/18:

IMG_1093 IMG_1233

For 4/21/18 to 4/27/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday Work – 4/21/18

  • Clean up and loadout
  • Interior work
  • Install curtainwall – Beacon Street

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street
  • Restoration of façade at hoist location

 Roof Myles (Exterior)

  • MEP insulation

Site

  • Point Park
    • Continue with excavation and underground
    • Continue setting landscape curb
  • Charlesgate
    • Continue Charlesgate bump out construction