For 4/7/18 to 4/13/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday Work – 4/7/18

  • Clean up and load out
  • Install site fencing and barriers at Charlesgate bumpout
  • Curb installation at point park
  • MEP insulation interior and roof

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street
  • Restoration of façade at hoist location – Beacon Street

 Roof Myles (Exterior)

  • MEP insulation

Site

  • Point Park
    • Continue with excavation and underground
    • Set road curb
    • Start setting landscape curb
  • Charlesgate
    • Saturday 4/7/18 – Install of fence and barriers ( See below no more parking in construction area )
    • Start demo of curbing and sidewalk
    • Drill and install traffic light foundation