Myles Standish Hall – Construction Activity – For 3/3/18 to 3/16/18:
For 3/3/18 to 3/9/18:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 3/3/18
- Interior work
- Staging removal – Beacon Street and Point
- Clean up and loadout
Demolition/Loadout
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps
Masonry Restoration (Exterior – Bay State Road & Beacon Street)
- Continue with masonry restoration and demolition – Bay State Road & Beacon Street
- Restoration of façade at hoist location – Beacon Street
Roof Myles (Exterior)
- MEP insulation
Site
- Point Park
- Starting excavation of asphalt for park construction
For 3/10/18 to 3/16/18:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 3/10/18
- Clean up and loadout
- Power shutdown – Myles & Annex
Demolition/Loadout
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps
Masonry Restoration (Exterior – Bay State Road & Beacon Street)
- Continue with masonry restoration and demolition – Bay State Road & Beacon Street
- Restoration of façade at hoist location – Beacon Street
Roof Myles (Exterior)
- MEP insulation
Site
- Point Park
- Start drilling well points and installation of drainage
- Charlesgate Bump Out
- Continue with construction of bump out