Myles Standish Hall – Construction Activity – For 3/3/18 to 3/16/18:

For 3/3/18 to 3/9/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday Work – 3/3/18

  • Interior work
  • Staging removal – Beacon Street and Point
  • Clean up and loadout

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street
  • Restoration of façade at hoist location – Beacon Street

Roof Myles (Exterior)

  • MEP insulation

Site

  • Point Park
    • Starting excavation of asphalt for park construction

 

For 3/10/18 to 3/16/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday Work – 3/10/18

  • Clean up and loadout
  • Power shutdown – Myles & Annex

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street
  • Restoration of façade at hoist location – Beacon Street

Roof Myles (Exterior)

  • MEP insulation

Site

  • Point Park
    • Start drilling well points and installation of drainage
  • Charlesgate Bump Out
    • Continue with construction of bump out