Myles Standish Hall – Construction Activity – For 2/17/18 to 2/23/18
For 2/17/18 to 2/23/18:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 2/17/18
- Interior work – Plumbing
- Clean up and loadout
Demolition/Loadout
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps
Masonry Restoration (Exterior – Bay State Road & Beacon Street)
- Continue with masonry restoration and demolition – Bay State Road & Beacon Street
Man and Material Hoist
- Crane will be onsite to remove the man and material hoist
Roof Myles (Exterior)
- MEP insulation
For questions, please contact Brian Kelley or visit our website for more information.