Joan & Edgar Booth Theatre and College of Fine Arts Production Center – Construction Activity – November 29, 2017 through December 11, 2017
For November 29, 2017 through December 11, 2017:
- Permitted by the Town of Brookline and in accordance with the approved Construction Management Plan, authorized work hours are 7 a.m. to 7 p.m. on weekdays, and Saturdays from 8:30 a.m. to 6 p.m. Sunday work schedules must be requested and approved by the Town.
- Brookline Police details will continue to be posted at the construction site entrance gate at Dummer Street, to ensure public safety. The safety of our community is our highest priority, so we ask that you please pay close attention to posted signs, police, and safety personnel.
- Completion of Dummer Street landscaping placement
- Completion of paving at the north plaza
- Pavement saw cutting at the north plaza
- Finishing concrete at the north, east, and west exterior plazas
- Finishing metal panel installation in the lobby
- Installation of lighting in the ceiling trusses in the black box theatre
Key Construction Activities
- Complete landscaping
- Install prefabricated benches at the north plaza
- Install bituminous curbs in the west parking lot
- Install line striping in the parking garage on levels B1 and B2