Myles Standish Hall – Construction Activity – 7/29/17 to 8/4/17
For 7/29/17 to 8/4/17:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 7/29/17
- Interior wall framing/taping/sanding – Annex
- Install bathroom tile – Annex
- Interior painting – Annex
- Install round top windows and caulking – Annex
- Exterior façade demolition – Beacon Street
- Clean up and loadout – Bay State Road
Verizon Off-Hours Work – 7/30/17 to 8/3/17
- Verizon has informed us that they will be working on site from 7:00 p.m. to 6:00 a.m. from Sunday to Wednesday. Verizon’s work is unrelated to the project.
Demolition/Loadout
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps
Masonry Restoration (Exterior – Bay State Road and Beacon Street)
- Continue masonry restoration and demolition – Bay State Road & Beacon Street
- Continue installation of staging and fraco – Bay State Road, Beacon Street, and the Point
Annex
- Install window waterproofing and blocking
- Install windows and wood trim
- Brick restoration – Annex alley
- Install stairwell framing and drywall
- Install basement wall framing
- Load out of demolition debris – Bay State Road
- Site deliveries – Bay State Road
Roof Myles (Exterior)
- Continue with roof demolition
Site Utility Work
- Utility cut and cap work – Beacon Street
- Install man and material hoist – Beacon Street
For questions, please contact Brian Kelley.