Myles Standish Hall – Construction Activity – 6/3/17-6/9/17

For 6/3/17 to 6/9/17:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 6/3/17
- Work on valance units – Upper floors
- Install staging – Bay State Road
- Clean up and loadout – Bay State Road
- Annex interior demolition and loadout – Bay State Road
Verizon Off-Hours Work – 6/4/17 to 6/8/17
- Verizon has informed us that they will be working on site from 7:00 p.m. to 6:00 a.m. from Sunday to Wednesday. Verizon’s work is unrelated to the project.
Fire Alarm Testing – 6/5/17 to 6/9/17
- The electrician will continue running a test of the fire alarm system on the construction-side of Myles. During this time, the strobe lights will be going off and minimal sound will be emitted through the speakers as needed. The work is expected to continue intermittently throughout the week. Please do not contact the Boston Fire Department during the testing. BFD will be notified in the event of an emergency.
Demolition/Loadout
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps
- Demolition of boiler room – Load out on Bay State Road
Masonry Restoration (Exterior – Bay State Road and Beacon Street)
- Continue masonry restoration – Bay State Road & Beacon Street
- Continue installation of staging and fraco – Bay State Road, Beacon Street, and the point
Annex
- Window removal
- Load out of demolition debris – Bay State Road
- Demolition of vault – Bay State Road
- Demolition of roof
- Masonry restoration – Annex alley
- Installation of stair tower – Beacon Street
- Site deliveries – Bay State Road
Roof Myles (Exterior)
- Continue with temporary roof parapets
Site Utility Work
- Utility work at Bay State Road and Beacon Street
For questions, please contact Brian Kelley or visit our website for more information