Myles Standish Hall – Construction Activity – 5/20/17 – 5/26/17

For 5/20/17 to 5/26/17:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 5/20/17
- Install valance units – Upper floors
- Install staging – Bay State Road
- Clean up and loadout – Bay State Road
- Floor mitigation – Floors 1-9
Verizon Off-Hours Work – 5/21/17 to 5/26/17
- Verizon has informed us that they will be working on site from 7:00 p.m. to 6:00 a.m. from Sunday to Wednesday. Verizon’s work is unrelated to the project.
Fire Alarm Testing – 5/22/17 to 5/26/17
- The electrician will continue running a test of the fire alarm system on the construction-side of Myles. During this time, the strobe lights will be going off and minimal sound will be emitted through the speakers as needed. The work is expected to continue intermittently throughout the week. Please do not contact the Boston Fire Department during the testing. BFD will be notified in the event of an emergency.
Demolition/Loadout
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps
- Demolition of boiler room – Load out on Bay State Road
Masonry Restoration (Exterior – Bay State Road and Beacon Street)
- Remedial restoration work off of fraco and swing staging – Bay State Road
- Continue masonry restoration – Beacon Street
- Continue installation of windows and screens
- Install staging and fraco – Bay State Road & Annex alley
- Begin masonry restoration work – Bay State Road & Beacon Street
Annex
- Window removal
- Load out of demo – Bay State Road
- Demolition of vault – Bay State Road
- Demolition of roof
- Masonry restoration – Annex alley
Roof (Exterior)
- Continue roof removal
Site Utility Work
- Install phase 2 site fencing at Annex and Myles
- Utility work at Bay State Road and Beacon Street