Myles Standish Hall – Construction Activity – 2/25/17 to 3/3/17
For 2/25/17 to 3/3/17:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 2/25/17
- Interior framing
- Interior cleaning
- Masonry cleaning on staging on the Bay State Road side of building
- Continue with hoist removal – Will be taking lane on Beacon Street for loading trailers. All permitting has been procured from the City.
Verizon Off-Hours Work – 2/26/17 to 3/2/17
- Verizon has informed us that they will be working on site from 7:00 p.m. to 6:00 a.m. from Sunday to Wednesday. Verizon’s work is unrelated to the project.
Snow Removal
- During any snow events snow, removal operations may be occurring at all hours in order to keep up with the snow and get the site ready for workers. These operations will require equipment, trucking, and manpower.
Demolition
- Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
- Beacon Street – Demo loading dock and start demo of façade where hoist was located.
Masonry Restoration (Exterior – Bay State Road and Beacon Street)
- Continue rebuilding exterior façade on the Beacon Street and Bay State Road sides of the building.
- Continue installation of limestone at 1st and 2nd
- Continue installation of windows.
Roof (Exterior)
- Continue installation of roofing flashing.
Site Utility Work
- No site utility work this week