Myles Standish Hall – Construction Activity – 2/18/17 to 02/24/17

Myles 2/18/17

For 2/18/17 to 02/24/17:
Deliveries Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

 Saturday Work – 2/18/17

  • Interior – Work in elevator hoistway
  • Interior framing
  • Masonry cleaning on staging on the Bay State Road side of the building

 Verizon Off-Hours Work – 2/19/17 to 2/23/17

  • Verizon has informed us that they will be working on site from 7:00 p.m. to 6:00 a.m. from Sunday to Wednesday. Verizon’s work is unrelated to the project.

 Snow Removal

  • During any snow events snow, removal operations may be occurring at all hours in order to keep up with the snow and get the site ready for workers. These operations will require equipment, trucking, and manpower.

Demolition

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Demolition of 1st floor (interior)

Masonry Restoration (Exterior – Bay State Road and Beacon Street)

  • Continue rebuilding exterior façade on the Beacon Street and Bay State Road sides of the building.
  • Continue installation of limestone at 1st and 2nd
  • Continue installation of windows.

 Roof (Exterior)

  • Continue installation of roofing flashing.

Alley Between Annex and Myles at Bay State Road (Exterior)

  • Continue exterior restoration.

Site Utility Work

  • No site utility work this week