For 10/1/16-10/7/16:

Myles 9/30/16 Myles 9/30/16

Deliveries

  • Subcontractors will receive deliveries all week from 7 a.m. until 6 p.m. on both Beacon Street and Bay State Road.

 Onsite Construction

 Saturday Work –  10/1/16 – On Saturday, the following construction work will be occurring onsite from 7 a.m. to 5 p.m. Activities will require workers, trucks, and equipment in point park.

  • Installation of relieving angles in alley on fraco
  • Clean and stock staging for masons in alley and on the Beacon Street and Bay State Road sides of the building.
  • Interior rough and interior demolition

Demolition

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Demolition and load out of basement
  • Demolition of floor 1 (interior)
  • Saw-cutting floors 2 – roof

Masonry Restoration (Exterior – Bay State Road and Beacon Street)

  • Continue rebuilding exterior façade above Annex off of swing staging.
  • Continue rebuilding exterior façade on the Bay State Road side of the building.

 Roof (Exterior)

  • Roof blocking and plywood installation at parapets
  • Temporary roofing of penetrations and parapet
  • Install roof steel – Will require crane on the Bay State Road side of the building.

Alley Between Annex and Myles at Bay State Road (Exterior)

  • Continue with masonry demo (Myles).
  • Start installation of relieving angles.
  • Continue with installation of brick (Annex)

Site Utility Work

  • Continue load out of soil from basement.
  • Continue with utilities within the site fence on the Beacon Street side of the building.

For questions, please contact Brian Kelley.