Myles Standish Hall – Construction Activity – 9/3/16 to 9/9/16

For 9/3/16 to 9/9/16:

Myles 9/1/16 Myles 9/1/16

Deliveries

  • Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

On-site Construction

There will be no work Saturday, 9/3/16 or Monday, 9/5/16 (Labor Day).

Beacon Street Work – 9/6/16 through 9/27/16 – Starting on Tuesday, 9/6/16, the following work will be occurring on Beacon Street between 9:30 a.m. and 3:30 p.m.

  • Site work – Bring water and drain lines in off of Beacon Street and into Myles.
  • Activities will require workers, trucks, and equipment on Beacon Street.
  • Traffic lanes will be shifted to accommodate two lanes of vehicular traffic in addition to a bicycle lane.

Demolition Abatement

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Continue with load out down chute (interior).
  • Demolition and load out of basement
  • Abatement on floor 1 (interior)
  • Demolition of floor 1 (interior)
  • Saw-cutting on floors 5, 6, and 7

Masonry Restoration (Exterior – Bay State Road and Beacon Street)

  • Continue rebuilding façade above Annex off of swing staging.
  • Continue installation of relieving angles on the Bay State Road and Beacon Street sides of the building.
  • Continue rebuilding exterior façade on the Bay State Road side of the building.

 Roof (Exterior)

  • Coring, saw-cutting, and demo of new holes and openings
  • Roof blocking and plywood installation at parapets
  • Temporary roofing of penetrations and parapet

Alley Between Annex and Myles at Bay State Road ( Exterior )

  • Continue installation of staging.
  • Continue removal of windows.
  • Start masonry demo.

Site Utility Work

  • Continue load out of soils from basement.

For questions, please contact Brian Kelley.