Myles Standish Hall – Construction Activity – 9/3/16 to 9/9/16
For 9/3/16 to 9/9/16:
Deliveries
- Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
On-site Construction
There will be no work Saturday, 9/3/16 or Monday, 9/5/16 (Labor Day).
Beacon Street Work – 9/6/16 through 9/27/16 – Starting on Tuesday, 9/6/16, the following work will be occurring on Beacon Street between 9:30 a.m. and 3:30 p.m.
- Site work – Bring water and drain lines in off of Beacon Street and into Myles.
- Activities will require workers, trucks, and equipment on Beacon Street.
- Traffic lanes will be shifted to accommodate two lanes of vehicular traffic in addition to a bicycle lane.
Demolition Abatement
- Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
- Continue with load out down chute (interior).
- Demolition and load out of basement
- Abatement on floor 1 (interior)
- Demolition of floor 1 (interior)
- Saw-cutting on floors 5, 6, and 7
Masonry Restoration (Exterior – Bay State Road and Beacon Street)
- Continue rebuilding façade above Annex off of swing staging.
- Continue installation of relieving angles on the Bay State Road and Beacon Street sides of the building.
- Continue rebuilding exterior façade on the Bay State Road side of the building.
Roof (Exterior)
- Coring, saw-cutting, and demo of new holes and openings
- Roof blocking and plywood installation at parapets
- Temporary roofing of penetrations and parapet
Alley Between Annex and Myles at Bay State Road ( Exterior )
- Continue installation of staging.
- Continue removal of windows.
- Start masonry demo.
Site Utility Work
- Continue load out of soils from basement.
For questions, please contact Brian Kelley.