Myles Standish Hall – Construction Activity – 8/27/16 – 9/2/16
For 8/27/16 – 9/2/16:
Deliveries
- Subcontractors will receive deliveries all week between 7 a.m. and 5 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 8/27/16 – Permission and permitting have been secured from the City to work from 7 a.m. to 5 p.m.
- Interior demo
- Activities will require workers, trucks, and equipment in point park area and on Beacon Street.
- Hoist will be running on Beacon Street.
Saturday 9/3/16 through Monday 9/5/16 – There will be no work during the holiday weekend and Labor Day.
Demolition Abatement
- Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
- Continue with load out down chute (interior).
- Demolition and load out of basement
- Abatement on floor 1 (interior)
- Demolition of floors 1 and 2 (interior)
Masonry Restoration (Exterior – Bay State Road and Beacon Street)
- Start masonry demo in Annex alley.
- Continue with masonry façade demo on the Beacon Street side of the building.
- Continue with rebuilding façade above the Annex off of swing staging.
- Continue installation of relieving angles on the Bay State Road and Beacon Street sides of the building.
- Continue rebuilding exterior façade on the Bay State Road side of building.
Roof (Exterior)
- Coring, saw-cutting, and demo of new holes and openings
- Roof blocking and plywood installation at parapets
- Temporary roofing of penetrations and parapet
Alley Between Annex and Myles at Bay State Road (Exterior)
- Continue installation of staging.
- Continue removal of windows.
- Start masonry demo.
Site Utility Work
- Continue load out of soils from basement at Beacon Street.
For questions, please contact Brian Kelley .