Myles Standish Hall – Construction Activity – 8/13/16 – 8/19/16

For 8/13/16 to 8/19/16:

Myles Roof 8/12/16 Myles Facade 8/12/16

Deliveries

  • Subcontractors will receive deliveries all week between 7 a.m. and 5 p.m. on both Beacon Street and Bay State Road.

 

Onsite Construction

 

Saturday Work – 8/13/16 – Permission and permitting have been secured from the City to work from 7 a.m. to 5 p.m.

  • Annex alley – Start erecting staging for façade restoration.
  • Activities will require workers, trucks, and equipment in point park area and alley.

 

Demolition Abatement

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Continue with load out down chute (interior).
  • Demolition and load out of basement.
  • Abatement on floor 1 (interior).
  • Demolition of floors 3, 4, and 5 (interior).

 

Masonry Restoration (Exterior)

  • Continue with masonry demo on the Bay State Road side of the building.
  • Continue with concrete repairs on the Beacon Street side of the building.
  • Continue with masonry façade demo on the  Beacon Street side of building.
  • Continue with masonry demo on swing above the Annex.
  • Continue installation of relieving angles on the Bay State Road side of the building.
  • Start rebuilding exterior façade on the Bay State Road side of the building.

 

Roof (Exterior)

  • Continue with layout and installation of concrete masonry units (CMU) at parapet on the Bay State Road side of the building.
  • Coring, saw-cutting, and demo of new holes and openings.
  • Roof blocking and plywood installation at parapets.
  • Temporary roofing of penetrations and parapet.

 

Alley Between Annex and Myles at Bay State Road

  • Continue install of staging.
  • Start removal of windows.
  • Start masonry demo.

 

Site Utility Work

  • Continue installation of new sewer line to Annex at the corner of Bay State Road and Raleigh Street.

 

For questions, please contact Brian Kelley.