For 8/13/16 to 8/19/16:
Deliveries
- Subcontractors will receive deliveries all week between 7 a.m. and 5 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 8/13/16 – Permission and permitting have been secured from the City to work from 7 a.m. to 5 p.m.
- Annex alley – Start erecting staging for façade restoration.
- Activities will require workers, trucks, and equipment in point park area and alley.
Demolition Abatement
- Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
- Continue with load out down chute (interior).
- Demolition and load out of basement.
- Abatement on floor 1 (interior).
- Demolition of floors 3, 4, and 5 (interior).
Masonry Restoration (Exterior)
- Continue with masonry demo on the Bay State Road side of the building.
- Continue with concrete repairs on the Beacon Street side of the building.
- Continue with masonry façade demo on the Beacon Street side of building.
- Continue with masonry demo on swing above the Annex.
- Continue installation of relieving angles on the Bay State Road side of the building.
- Start rebuilding exterior façade on the Bay State Road side of the building.
Roof (Exterior)
- Continue with layout and installation of concrete masonry units (CMU) at parapet on the Bay State Road side of the building.
- Coring, saw-cutting, and demo of new holes and openings.
- Roof blocking and plywood installation at parapets.
- Temporary roofing of penetrations and parapet.
Alley Between Annex and Myles at Bay State Road
- Continue install of staging.
- Start removal of windows.
- Start masonry demo.
Site Utility Work
- Continue installation of new sewer line to Annex at the corner of Bay State Road and Raleigh Street.
For questions, please contact Brian Kelley.