- Site preparation and enabling construction activities will continue as permitted by the Town of Brookline and in accordance with the approved Construction Management Plan.
- Authorized work hours are 7 a.m. to 7 p.m. on weekdays, and Saturdays from 8:30 a.m. to 6 p.m.
Key Construction Activities
- Upcoming Saturday Work:
- Work is scheduled for the next three Saturdays (August 13th, 20th, and 27th). Pile driving operations and site excavation will continue.
- Now through September 2, 2016: Demolition, excavation, trenching, all underground site utilities installations, and foundation installation will be ongoing. Support of excavation work is ongoing. Pile driving operation for foundations has begun and will continue for the next 4 to 6 weeks and is expected to be complete September 2nd. Noise and vibrations can be expected from this pile driving operation.
- August 15th through August 19th: Eversource will be performing work on Essex Street and the power tie-in for 808 Commonwealth Ave is scheduled to begin August 15th.
- August 17th through August 22nd: Work for a new domestic water tie in for 808 Commonwealth Avenue will begin August 17th. During this work, the building will be closed and unable to be occupied starting at 6 a.m. Wednesday, August 17th. The building will re-open for use and occupancy at 6 a.m. on Tuesday, August 23rd.