BU Theatre Center – Construction Activity – 7/29/16 – 8/7/16

For July 29, 2016 through August 7, 2016

  • Site preparation and enabling construction activities will continue as permitted by the Town of Brookline and in accordance with the approved Construction Management Plan.
  • Authorized work hours are 7 a.m. to 7 p.m. on weekdays, and Saturdays from 8:30 a.m. to 6 p.m.
  • Parking and access to the site is closed to the public and University faculty and staff through the end of the project – projected to be in August 2017.P
  • The parking access ramp from Commonwealth Avenue has been demolished.
  • The safety of our community is our highest priority, so we ask that you please pay close attention to posted signs and safety personnel.

 

Key Construction Activities

Now through September 2, 2016

  • Demolition, excavation, trenching, all underground site utilities installations, and foundation installation will be ongoing.

Upcoming Saturday Work

  • July 30th weekend (Saturday) – Removal of demolition debris is scheduled to occur on Saturday, July 30th.
  • August 6th weekend (Saturday) – Pile installation for building foundation support will be performed on Saturday, August 6th.

July 30th through August 5th

  • Repair of the tel/data conduits at Dummer street sidewalk is underway. Expect to place concrete sidewalk week of 8/1.

August 1st through August 14th

  • Remaining pile installation for the support of excavation will resume on Monday, 8/1 to the west of the 808 Commonwealth Avenue and will continue along Commonwealth Avenue for approximately one week.
  • Pile installation for building foundation support will start Thursday, 8/4. It is anticipated that the pile installation sequence will begin at the lower portion of the site between 808 and 830 Commonwealth Avenue, and then move to the south portion of the site along Dummer Street for approximately one to two weeks. Once the south portion of the site is complete, pile installation will move to the north portion of the site along Commonwealth around the 3rd week of August.
  • Noise and vibrations can be expected from this pile driving operation.

For questions please contact Kristi Dowd.