Myles Standish Hall – Construction Activity – 7/30/16 – 8/5/16

For 7/30/16 – 8/5/16

Deliveries
Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road

Onsite Construction

Saturday 07/30/16 – No work

Demolition Abatement

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Continue with load out down chute (interior).
  • Demolition and load out of basement.
  • Abatement on floors 2, 3, and 4 (interior).
  • Demolition of floors 5, 6, and 7 (interior).

Masonry Restoration (Exterior)

  • Continue with masonry demo on the Bay State Road side of the building.
  • Continue installation of concrete masonry units (CMU) at the 9th floor on the Beacon Street side of the building.
  • Continue with concrete repairs on the Beacon Street and Bay State Road sides of building.
  • Continue with masonry facade demo on the Beacon Street side of building at the 9th floor.
  • Continue with masonry demo on swing above the Annex.
  • Continue installation of relieving angles on the Bay State Road side of building.

Roof (Exterior)

  • Continue with layout and installation of CMU at parapet on the Bay State Road side of the building.
  • Coring and sawcutting new holes and openings.
  • Temporary roofing of penetrations and parapet.

Alley Between Annex and Myles at Bay State Road

  • Continue with forming for concrete at transformer pad.
  • Waterproofing at transformer pad.
  • Pour topping slab – Requires pump truck and concrete trucks at Bay State Road.
  • Site work – Continue to bring drain line in off of Bay State Road and then into the alley.

Myles 7/28/16 Myles 7/28/16

For questions, please contact Brian Kelley.

View all posts