Myles Standish Hall – Construction Activity – 6/18/16 to 6/24/16
For 6/18/16 – 6/24/16:
Deliveries
- Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
No work – Saturday 06/18/16
Man and Material Hoist Construction
- Excavate for hoist pad on Bay State Road side of building – Exterior
- Form and pour hoist pad on Bay State Road side of building – Exterior
Demolition Abatement
- Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster.
- Continue with load out down chute – Interior
- Demolition and load out of basement.
- Demolition after abatement at buffer zone on floors 5 and 6.
- Demolition of floors 8 and 9.
- Start demolition of existing freight elevator shaft – Interior
Masonry Restoration (Exterior)
- Continue with removal of windows on the Bay State Road side of the building.
- Continue with masonry demo on the Bay State Road side of the building.
- Start installation of staging on the Beacon Street side of the building.
- Start removal of windows on the Beacon Street side of the building.
Roof (Exterior)
- Continue with demolition of roof curbs and penthouse, and installation of temporary roof curbs.
Site Work
- Start excavation for transformer pad foundation in the alley – Excavator and trucks for load out of dirt.
For questions, please contact Brian Kelley.