CILSE – Construction Activity – 6/12/16
For the week of June 12, 2016:
On the Commonwealth Avenue side of the building, the glass replacement is expected to be completed and sealing around replaced glass will take place. Installation of window frames, glass, and insulation will continue on the Cummington Mall and Morse Auditorium sides of the building. Framing and sheathing from the swing staging will continue on the Cummington Mall side. Roofing will be ongoing.
Wall framing will continue on floors 7, 8, and 9. In-wall electrical and plumbing and above ceiling electrical, mechanical, and plumbing will continue on floors 2 through 9. Installation of drywall will continue on floors 2, 3, 4, and 5. Painting on floors 2, 3, and 4 will continue. Shielded room mock-up testing will take place on the 9th floor. Wall layout and MEPs will be ongoing on the 1st floor. Service elevator installation will be ongoing. Removal of curtain wall at the 3-5 Cummington Mall loading dock is tentative for next week, in addition to rebar placement on the connector.
Police details will continue to man the construction gates along Commonwealth Avenue to ensure public safety. The safety of our community is our highest priority, so we ask that you please pay close attention to posted signs, police, and safety personnel.
For questions please contact Brian Kelley.