CILSE – Construction Activity – Week of 6/6/16
For the week of June 6, 2016:
The team will continue replacement of glass units on the Commonwealth Avenue side of the building. Installation of window frames and glass, as well framing and sheathing from the swing staging, will continue on the Cummington Mall and Morse Auditorium sides of the building.
Wall framing will continue on floors 7, 8 and 9. In-wall electrical and plumbing and above-ceiling electrical, mechanical, and plumbing will continue on floors 2 through 9. Installation of drywall on floors 2 through 5 will continue. Shielded room mock-up will continue on the 9th floor. Wall layout and MEPs will be starting on the 1st floor. Service elevator installation will be ongoing.
Police details will continue to man the construction gates along Commonwealth Avenue to ensure public safety. The safety of our community is our highest priority, so we ask that you please pay close attention to posted signs, police, and safety personnel.
For questions please contact Brian Kelley.