Myles Standish Hall – Construction Activity – Week of 5/28/16
For the week of May 28, 2016:
Eversource Limited Power Outage
- Eversource has informed us that on Wednesday night/early Thursday morning (5/26), from 12:01 a.m. until 8:00 a.m., they will be temporarily shutting down power in the neighborhood. Eversource has sent reverse 911 phone calls to the properties that will be affected by this power outage.
Deliveries
- Subcontractors will be receiving deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday 5/28/16 and Monday 5/31/16
- No work Saturday or Monday (holiday).
Man and Material Hoist Construction
- Remove windows and start demo of exterior wall off of boom lift on Beacon Street side of building – Exterior.
Demolition Abatement
- Load out at Beacon Street with crane – Load out all carpet and wood floors 9-1 (pre–abatement demo) and load out roof demo.
- Continue with demolition of stairway for chute – Interior.
- Abatement of floors 9, 1, and basement – Interior.
- Annex alley demolition – Continue interior demolition of basement and 1st floor for one-story demo, start exterior demo of one-story addition connected to Annex, and demo all exterior MEP attached to façade in the alley. All load out will be by dumpster in the alley.
Masonry Restoration (Exterior)
- Continue to install staging on Bay State Road side of building.
- Start removal of windows on Bay State Road side.
- Start masonry demo on Bay State Road side.
Roof (Exterior)
- Continue with abatement and demolition.
- Roofer will mobilize with a crane on Beacon Street side of building. They will start roof removal and scale pan materials to a dumpster on the ground level.
- Start roof removal and installation of roof curbs.
MEP (Interior)
- Temporary fire alarm installation and testing.
For questions, please contact Brian Kelley.