Exterior curtain wall work will continue on the west elevation on floors 4 and 5 and on the north elevation on floor 9. Exterior wall framing and sheathing will continue on the east elevation, and swing staging work will begin on the south elevation. Installation of the air and vapor barrier will continue on the south elevation, and installation of window and wall screen panels will begin. On the roof, wind screen and solar curb installation will continue.
Wall framing will continue on floors 7 and 8. In-wall data, electrical, and plumbing will be installed on floors 4 through 6. On the 4th floor, wallboard prep, in-wall inspections, and installation of wallboard will take place. Electrical rooms, data rooms, and emergency electrical rooms are being built from the 2nd floor up to 8th. Mechanical, plumbing, and electrical work will continue above the ceiling up to the 8th floor. Concrete pours are scheduled for the remaining 1st floor fMRI area. Patching and installation of spray-on fire proofing and elevator tube steel will continue. Installation of piping on the 9th floor to the rooftop equipment will take place.
Police details will continue to man the construction gates along Commonwealth Avenue to ensure public safety. The safety of our community is our highest priority, so we ask that you please pay close attention to posted signs, police, and safety personnel.
For questions please contact Brian Kelley.