CILSE – Construction Activity – Week of 1/10/16
For the week of January 10, 2016:
The project will be operational this weekend loading mechanical equipment to the roof on both Saturday (1/9) and Sunday (1/10).
During the week the project team will be topping off the building’s structural steel. The concrete decks will follow structural steel. We have scheduled concrete pours on Wednesday (1/13), Thursday (1/14), and Friday (1/15). The construction hoist will be in final stages of installation and will be utilized to access upper floors.
Steel deliveries will continue to arrive each day between 7 AM and 9 AM. There will be a large volume of concrete trucks entering and exiting the site during the course of the day from Wednesday (1/13) through Friday (1/15). We will also be accepting deliveries off of Cummington Mall between the hours of 6 AM and 7 AM throughout the week.
Police details will continue to man the construction gates along Commonwealth Avenue to ensure public safety. The safety of our community is our highest priority, so we ask that you please pay close attention to posted signs, police, and safety personnel.
The schedule of communications meetings for the spring semester has yet to be determined. Once a schedule is set, it will be posted on the project website and included in weekly updates.
For questions please contact Brian Kelley.