CILSE – Construction Activity – Week of October 25, 2015
For the week of October 25, 2015:
This past week the project team began installation of the large crawler crane. The crane installation will be completed on Saturday (10/24). Structural steel installation will progress rapidly over the next few weeks. Please be aware that there will be an increased amount of truck traffic during the morning hours next week as the steel is delivered to site. Safety continues to be a main focus of the entire project team and there will be additional police details on-site next week to manage the increase in truck traffic. Please continue to follow the path identified by construction barricades and signs and be ready to take direction from police officers and project staff when necessary.
Saturday (10/24) – The crawler crane erection will be completed. Pedestrian traffic will be diverted to a temporary sidewalk during the hours of 7 AM and 10 AM. The crane will remain inside the project fence and will be on-site until February 2017.
Monday (10/26) – The project team will be installing structural steel. There will be 4 tractor trailer deliveries between 7 AM and 9 AM.
Tuesday (10/27) – Structural steel installation will continue. There will be 4 tractor trailer deliveries between 7 AM and 9 AM.
Wednesday (10/28) – Structural steel installation will continue. There will be 3 to 6 tractor trailer deliveries between 7 AM and 9 AM.
Thursday (10/29) – Structural steel installation will continue. There will be 3 to 6 tractor trailer deliveries between 7 AM and 9 AM.
Friday (10/30) – Structural steel installation will continue. There will be 3 to 6 tractor trailer deliveries between 7 AM and 9 AM.
In addition to construction activities inside the site, the utility companies will be performing work on Commonwealth Avenue on Monday (10/26). This work will take place between the hours of 9:30 AM to 3:30 PM and will result in alternating traffic lane closures. Traffic lanes will be clear of construction activities beginning Tuesday.
The construction team will hold regularly scheduled communications meetings on the first Thursday of every month at 10:30 AM and the third Wednesday of every month at 1:00 PM. These meetings are open to the University community and will be held in the project site office at 602 Commonwealth Avenue (basement of Morse Auditorium) unless otherwise noted. The schedule of these meetings is set through the fall semester (December 2015) and will be reexamined and/or reconfirmed for each semester as the project progresses.
The next communications meeting will be November 5th at 10:30 AM in the project site office at 602 Commonwealth Avenue.