CILSE – Construction Activity – Week of July 20, 2015
For the week of July 20, 2015:
The contractor will be working on Saturday (7/18) to install of pressure-injected footings (PIFs). Please note that work will be taking place on Saturdays through the end of July and into August.
Next week, the project team will continue to drive and grout PIFs within the site. Wednesday morning (7/22), concrete will be poured and the mini-pile operation in the south east corner of the site will begin. A crane will be on site unloading rebar onsite in preparation for future concrete pours on Tuesday (7/21).
In the rear alley between 3-5 Cummington Mall and the College of Communication, temporary fencing will be set up and excavation and underground utility work will be taking place throughout the week. Please be aware that his work will extend from the alley into Cummington Mall. The north sidewalk on Cummington Mall will be closed for the week and the roadway will be cut down to one lane from 6 AM-3PM daily.
For questions please contact Brian Kelley.