For the week of June 29, 2015:
Saturday – 6/27
Removal of street lights and installation of temporary street lighting.
Monday – Friday 6/29 – 7/3
Installation of the earth retention system will continue. A drilling rig will be on site to support this operation. Trucking of excavated materials will begin, which will result in significant truck traffic entering and leaving the site.
Thursday – Friday 7/2 – 7/3
Installation of pressure injected footings (PIF) will begin. This operation will cause loud banging and localized vibration.
For questions please contact Brian Kelley.