CILSE – Construction Activity – Week of June 22, 2015

Week of June 22, 2015:

On Saturday, June 20, a vacuum truck will be on site installing monitoring wells. For the rest of the week, installation of the earth retention system will continue A drilling rig will be on site to support this operation. Trucking of excavated materials will also begin next week, which will result in significant truck traffic entering and leaving the site. Police details will be present to control traffic.

For questions please contact Brian Kelley.