Engineering Product Innovation Center Construction Activity for the Period of July 8 – July 12
Anticipated construction activities for the week of July 8 – July 12:
1. 744 Commonwealth Ave – The contractor will be performing the following activities:
a. Continue to close up the new walls and begin drywall taping
b. Install new overhead ductwork
c. Begin concrete floor polishing
d. On the roof, the contractor will continue to install the equipment supports for the new HVAC equipment.
2. 750 Commonwealth Ave – The contractor will be performing the following activities:
a. Basement – Install new electric work to the boiler room and to the new spaces on the 1st floor.
b. 1st Floor – Continue install new electrical wiring, HVAC ductwork and piping, new walls, and sprinkler piping. Install new gas line piping through the 730 Comm Ave garage.
c. 2nd Floor – Install new ducts from the first floor to the roof.
d. Roof Work – Begin vacuuming stone off the roof and take delivery of new roof material
e. Exterior – Begin new work construction on the Commonwealth Avenue, continue masonry work on Mass Pike side of building.