Engineering Product Innovation Center Construction Activity for the Period of June 10 – June 14

1. 744 Commonwealth Ave – The contractor will be performing the following activities:

a. Begin to frame the walls and start construction on the new ramp that will connect building 744 Comm and 750 Comm
b. Begin to install the new electric wiring
c. On the roof, the contractor will start laying out the locations of the new HVAC equipment

2. 750 Commonwealth Ave – The contractor will be performing the following activities:
a. Basement – Install new sanitary lines and vents and new electric wiring
b. 1st Floor – Install electrical wiring, overhead ductwork, and plumbing to the new bathroom
c. 2nd Floor – Relocate existing HVAC equipment and begin cutting openings in the floor for new ductwork
d. Exterior – Begin the demolition of the existing building façade.

Please note: On Monday night, 6/10, and Tuesday night, 6/11, the contractor will be erecting scaffolding on the Mass Pike side of the building. This will be done off-hours, but you may see the scaffolding through windows facing the Mass Pike. The contractor will be doing work on the exterior of the building on the Mass Pike during normal business hours starting this week.