New Balance Field Construction Activity for the Period of March 25 – March 29
Anticipated construction activities for the week of March 25 – March 29:
**The contractor will be working on Saturday, 3/23/2013, beginning at 8:00am**
1. Site Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expected general construction noise from the equipment, and construction traffic in the form of dump trucks on the surrounding streets. Excavation and hauling of soils will continue and truck activity for the removal of the excavated soils will be coordinated and Police details will be present to help manage traffic flow.
2. Underground Site Utilities – Continuing for the next several weeks is the installation of underground utilities within the site. Underground utility construction activities will be performed concurrently with the site work, and consist of similar construction techniques such as excavators, dump trucks, etc.
3. Concrete Work: The delivery of concrete materials to the site will continue. You can expect construction traffic in the form of deliveries of rebar, formwork, and concrete to continue throughout the week, and installation of cast in place concrete foundations is ongoing.
4. Precast Concrete: Delivery of trailer loads of precast concrete will be entering the site for offloading. There will be several deliveries of precast concrete each day. These precast concrete units are being set with the crane. Police details will be present to help manage traffic flow.