News
West Campus Dining Expansion – Construction Update – 5/12/23
General Project Updates Corridor flooring, office carpeting, sheetrock patching and painting, installation of vestibule storefronts, and electrical and data installations have been completed. On the exterior of the building, the team worked on site clean-up for Commencement Weekend, painting the temporary door, roofing at the canopy, re-location of temp fencing, More
West Campus Dining Expansion – Construction Update – 5/5/23
General Project Updates Tile flooring installation is complete. Mechanical ceiling registers, grilles, and diffusers were installed. Mechanical insulation and the light fixture wiring and installation was completed. Millwork installation at the mail room and security desk was completed and the walls were painted. The refrigeration lines for the roof top... More
Kilachand Hall Phase 2 – Construction Update – 5/5/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 04/28/23
General Project Updates The rough HVAC install has been completed. Brick repairs at the new entrance have been made. The metal deck at the exterior part of the entrance has been welded, and the canopy posts have been installed. Wood framing on the ceiling of the canopy has been completed. Weekend... More
Kilachand Hall Phase 2 – Construction Update – 04/28/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
Kilachand Hall Phase 2 – Construction Update – 04/21/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 04/21/23
Weekend of April 22nd There will be contractors working on the ceiling in the vicinity of the security desk and the surrounding lobby area. Week of April 17th Inside, sheetrock, acoustic ceiling tile grid, ductwork insulation, and flooring are being installed. The team will also be installing the acoustic ceiling tile grid... More
Kilachand Hall Phase 2 – Construction Update – 4/14/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 4/14/23
Project Updates The drywall installation in the Residence Life offices is expected to be completed this Saturday, 4/15. The electrical cabling above the ceiling is about 75% complete, and the HVAC ductwork installation is about 90% complete. The exterior concrete and brick wall removal at the new building entrance was... More
West Campus Dining Expansion – Construction Update – 4/7/23
Project Updates The contractor is nearing the completion of the sheetrock installation and the mechanical rough-in work. Sheetrock tapping has begun. The ACT ceilings in the egress corridor will be removed this Saturday, April 8th. Structural steel installation for the canopy has begun. Once done, the removal of the exterior concrete... More