CFA Renovations – Construction Update – 11/01/19
During November 1st – November 8th: (Please note that there is work scheduled for Saturday November 2nd): General: Temporary signs are posted to help direct you through the first floor. The main building access is through the west entrance near the Concert Hall. Stair access directly off Comm Ave will be open and closed periodically... More
Howard Thurman Center – Construction Update – 11/01/19
Week of November 4, 2019 General: Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the parking... More
Geothermal Well Drilling Initiative – Construction Update – 11/01/19
During the week of November 4th: Parking Lot N The drilling subcontractor will continue drilling at GT-5 and anticipates moving to complete drilling at GT-4. The site subcontractor will be handling the soil material in the settlement basin for removal and transportation to the disposal facility. They will also be power... More
Geothermal Well Drilling Initiative – Construction Update – 10/25/19
During the week of October 28th: Parking Lot N The drilling subcontractor will continue drilling within the cased borehole at GT-1. The site subcontractor will be placing the material into the settlement basin within the fenced-in area of the lot and will be handling the soil material for removal and transport... More
Howard Thurman Center – Construction Update – 10/25/19
During the week of October 28: General: Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the... More
CFA Renovations – Construction Update – 10/25/19
During October 25th - November 1st: (Please note that there is work scheduled for Saturday, October 26th): General: Temporary signs are posted to help direct you through the first floor. The main building access is through the west entrance near the Concert Hall. Stair access directly off Commonwealth Ave will be open and... More
Goldman School of Dental Medicine – Construction Update – 10/25/19
During the weekend of October 26: On Saturday, work will continue throughout the interior of the seven-story west addition and on the exterior of all elevations, where new terracotta and faux wood trim finish façade panels are being installed. Also, on Saturday, a crane will be set up within the... More
CFA Renovations – Construction Update – 10/18/19
During October 18th – October 25th: (Please note that there is work scheduled for Saturday, October 19th): General: Temporary signs are posted to help direct you through the first floor. The main building access is through the west entrance near the Concert Hall. Stair access directly off Commonwealth Ave will be open and... More
Geothermal Well Drilling Initiative – Construction Update – 10/18/19
During the week of October 21st: Parking Lot N The drilling subcontractor will continue drilling at GT-6 and setting the steel pipe casing for the geothermal well at GT-1. The site subcontractor will be placing the material into the settlement basin within the fenced-in area of the lot and will be... More
Howard Thurman Center – Construction Update – 10/18/19
During the week of October 21: General: Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the... More