Goldman School of Dental Medicine – Construction Update – 3/5/21
During the weekend of March 6: Starting Friday, March 5, at 8 p.m. and working through Saturday and Sunday, March 6 and 7, crews will be working in the first-floor Stair 1 elevator lobby. On Friday evening, the new elevator door frames will be installed. On Saturday and Sunday, workers... More
Center for Computing & Data Sciences – Construction Update – 2/26/21
During the weekend of February 27th Weather dependent, crews intend to work on site Saturday to continue removing formwork from the 4th floor of the tower’s core. Crews will also be reinstalling for the 5th floor, along with installing rebar at the 5th floor. Weather dependent, crews will return to the... More
Goldman School of Dental Medicine – Construction Update – 2/26/21
During the weekend of February 27: Starting Friday, February 26, at 8 p.m. and working through Saturday and Sunday, February 27 and 28, crews will be working in the Stair 1 lobbies on the fifth, sixth, and seventh floors to complete mechanical, plumbing, and electrical infrastructure work above the ceiling. More
Goldman School of Dental Medicine – Construction Update – 2/19/21
During the weekend of February 20: Starting Friday, February 19, at 8 p.m. and working through Saturday, February 20, and Sunday, February 21, crews will be working in Stair 1 lobbies on the second, third, and fourth floors to complete mechanical, plumbing, and electrical infrastructure work above the ceiling. The... More
Center for Computing & Data Sciences – Construction Update – 2/19/21
During the weekend of February 20th Crews will be on site Saturday to begin removing the formwork that was poured with concrete on Thursday from the 3rd floor. Work on reinstalling for the 4th floor pour will begin. Depending on the outcome of Friday’s storm, this activity may be superseded by... More
Center for Computing & Data Sciences – Construction Update – 2/12/21
During the weekend of February 13th Following Thursday’s concrete placement of the core, crews will be on site Saturday, February 13th, to remove the formwork that encased the concrete poured on Thursday and to begin reinstalling it for the concrete pour that will create the next level. This activity is... More
Goldman School of Dental Medicine – Construction Update – 2/12/21
During the weekend of February 13: There will be no work on-site this weekend. During the week starting February 15: Due to the Presidents Day holiday, there will be no work on-site on Monday, February 15. From Tuesday, February 16, through Friday, February 19, night-shift work will resume from 10 p.m. More
Center for Computing & Data Sciences – Construction Update – 2/5/21
During the weekend of February 6th Crews will be on site Saturday to continue to install rebar and formwork for the tower’s core. During the week of February 8th Installation of rebar and formwork will begin next to Sargent College for the bike shelter foundation. Following the completion of the concrete... More
Goldman School of Dental Medicine – Construction Update – 2/5/21
During the weekend of February 6: There will be no work on-site this weekend. During the week starting February 8: From Monday, February 8, through Friday, February 12, night-shift work will resume from 10 p.m. until 6 a.m. On Monday, plumbing crews will finish connecting the seventh-floor existing dental chairs and... More
Center for Computing & Data Sciences – Construction Update – 1/29/21
During the weekend of January 30th Crews will be on site Saturday to continue to install rebar and formwork at various locations for the tower’s foundation and core systems. During the week of February 1st The installation of site drainage infrastructure will occur at the east edge of the site, between... More