Category: Featured Content
Myles Standish Hall – Saturday Work – 12/9/17
Onsite Construction Clean up and loadout Staging removal – Beacon Street Interior painting
Myles Standish Hall – Construction Activity – 12/9/17 to 12/15/17
For 12/9/17 to 12/15/17: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 12/9/17
Onsite Construction Clean up and loadout Staging removal and installation Interior taping and sanding
Myles Standish Hall – Construction Activity – 12/2/17 to 12/8/17
For 12/2/17 to 12/8/17: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Joan & Edgar Booth Theatre and College of Fine Arts Production Center – Construction Activity – November 29, 2017 through December 11, 2017
For November 29, 2017 through December 11, 2017: Permitted by the Town of Brookline and in accordance with the approved […]
Myles Standish Hall – Construction Activity – 11/25/17 to 12/1/17
For 11/25/17 to 12/1/17: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 11/25/17
Onsite Construction Clean up and loadout Window caulking
Myles Standish Hall – Construction Activity – 11/18/17 to 11/24/17
For 11/18/17 to 11/24/17: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 11/18/17
Onsite Construction Coring – 1st Floor Overhead rough – 1st Floor Clean up and loadout Window caulking Roof installation
Joan and Edgar Booth Theatre & Boston University Production Center – Construction Activity – November 9, 2017 through November 27, 2017:
For November 9, 2017 through November 27, 2017: Permitted by the Town of Brookline and in accordance with the approved […]