Myles Standish Hall – Saturday Work – 4/21/18
Onsite Construction Clean up and loadout Interior work Install curtainwall Beacon Street
Goldman School of Dental Medicine – Construction Update – 4/13/18
During the week of April 16: We will continue drilling the first foundation piling in the area between the former […]
Myles Standish Hall – Construction Activity – For 4/14/18 to 4/20/18:
For 4/14/18 to 4/20/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Groundbreaking for “New” Goldman School of Dental Medicine
Dean says SDM is “on its way into and beyond the 21st century” 04.09.2018 By Sara Rimer. Photos by […]
Goldman School of Dental Medicine – Construction Update – 4/6/18
During the week of April 9: We will continue trucking operations associated with topsoil removal that began this week to […]
Myles Standish Hall – Construction Activity – 4/7/18 to 4/13/18
For 4/7/18 to 4/13/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. […]
Myles Standish Hall – Saturday Work – 4/7/18
Onsite Construction Clean up and loadout Interior work Install temp fencing and barriers at Charlesgate bump out
Goldman School of Dental Medicine – Construction Update – 3/30/18
During the weekend of March 30: We will continue weekend infrastructural work on the relocation of the traffic signal at […]
Myles Standish Hall – Construction Activity – For 3/31/18 to 4/6/18
For 3/31/18 to 4/6/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 3/31/18
Onsite Construction Clean up and loadout Interior floor prep Exterior relieving angle install Beacon Street