Category: Featured Content
Geothermal Well Drilling Initiative – Construction Update – 3/29/19
During the week of April 1: Park Test Well #3 The driller anticipates delivery of new drill rod on Monday […]
Geothermal Well Drilling Initiative – Construction Update – 3/22/19
During the week of March 25: Park Test Well #3 Driller has mobilized and drilled 225 feet through the overburden, […]
Goldman School of Dental Medicine – Construction Update – 3/22/19
During the weekend of March 23: The City of Boston has again issued a permit allowing GSDM to temporarily close […]
Geothermal Well Drilling Initiative – Construction Update – 3/15/19
During the week of March 18: Parking Lot Test Well #1 Fencing will be removed, and the parking areas will […]
Goldman School of Dental Medicine – Construction Update – 3/15/19
During the weekend of March 16: The City of Boston has issued a permit allowing GSDM to temporarily close East […]
BU Children’s Center – Construction Update – 3/15/19
Week of 3/23/19: The contractor will be mobilizing on site and will begin making the site ready for start of […]
Geothermal Well Drilling Initiative – Construction Update – 3/8/19
Week of 03/11/19 – 03/15/19: Parking Lot Test Well #1 Relocation of Rygan stockpile to storage area. Relocation of the […]
Goldman School of Dental Medicine – Construction Update – 3/8/19
During the weekend of March 9: Following this past week’s exciting “Steel Day” milestone—the start of structural steel supporting the […]
Historic, and Loud, Geothermal Drilling Gets Underway
If you’ve been anywhere near Boston University’s East Campus recently, you may have heard the echoing sound of drilling, particularly near the corner of Commonwealth Avenue and Granby Street.
Goldman School of Dental Medicine – Construction Update – 3/1/19
During the weekend of March 2: On Saturday, crews will be installing plywood on the interior of the windows along […]