Category: Featured Content
Kilachand Hall Phase 2 – Construction Update – 6/16/23
General: Daily Work Hours from 6 am-4 pm. (6 am for interior work per ISD permit) The Traffic Management Plan […]
Kilachand Hall Phase 2 – Construction Update – 06/09/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 6/9/23
General Project Updates Millwork was installed in the Residence Life spaces. In the dining hall, flooring was demolished, electrical wiring was […]
Kilachand Hall Phase 2 – Construction Update – 06/02/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 05/26/23
General Project Updates The Residence Life Offices moved from their temporary space into their newly renovated office space. While there […]
Kilachand Hall Phase 2 – Construction Update – 05/26/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 05/19/23
General Project Updates In the Residence Life Offices, ceiling tile work was completed, doors installed, electrical work completed, and millwork […]
Kilachand Hall Phase 2 – Construction Update – 05/19/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
Kilachand Hall Phase 2 – Construction Update – 5/12/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 5/12/23
General Project Updates Corridor flooring, office carpeting, sheetrock patching and painting, installation of vestibule storefronts, and electrical and data installations […]