General Project Updates Last week work on the new exterior walkway continued. Framing of the gluten-free area was completed. Preparation for […]
Kilachand Hall Phase 2 – Construction Update – 07/21/23
General Project Information Daily Work Hours from 6 am – 3 pm. (6 am for interior work) The Traffic Management Plan for […]
Kilachand Hall Phase 2 – Construction Update – 07/14/23
General Project Information Daily Work Hours from 6 am – 3 pm. (6 am for interior work) The Traffic Management Plan for […]
West Campus Dining Expansion – Construction Update – 07/14/23
General Project Updates This past week, excavation work on the new sidewalk was completed, and the site was prepped and […]
Kilachand Hall Phase 2 – Construction Update – 07/07/23
General Project Information Daily Work Hours from 6 am – 3 pm. (6 am for interior work per ISD permit) The Traffic […]
West Campus Dining Expansion – Construction Update – 07/07/23
General Project Updates This past week, exterior work began and excavation of the site’s utilities and stockpiling soil took place. Soffit […]
West Campus Dining Expansion – Construction Update – 6/30/23
General Project Updates This past week saw the following construction activity – metal stud framing, sheetrock installation, rough plumbing installation, […]
Kilachand Hall Phase 2 – Construction Update – 06/30/23
General Project Information Daily Work Hours from 6 am – 3 pm. (6 am for interior work per ISD permit) The Traffic […]
Kilachand Hall Phase 2 – Construction Update – 06/23/23
General Project Information Daily Work Hours from 6 am – 3 pm. ( 6 am for interior work per ISD permit) The […]
West Campus Dining Expansion – Construction Update – 06/23/23
General Project Updates Work is ongoing for the West Campus Dining Expansion and repairs to the West Campus steam line […]