Myles Standish Hall – Construction Activity – For 3/31/18 to 4/6/18
For 3/31/18 to 4/6/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 3/31/18
Onsite Construction Clean up and loadout Interior floor prep Exterior relieving angle install Beacon Street
Goldman School of Dental Medicine – Construction Update – 3/23/18
During the week of March 26: Work will continue at the School’s East Newton Street entrance to prepare for the […]
Myles Standish Hall – Construction Activity – For 3/24/18 to 3/30/18
For 3/24/18 to 3/30/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Construction Activity – For 3/17/18 to 3/23/18
For 3/17/18 to 3/23/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 3/17/18
Onsite Construction Clean up and loadout Interior work
Myles Standish Hall – Construction Activity – For 3/3/18 to 3/16/18 – CORRECTION
Correction to update sent 3/1/18: The work on the Charlegate Bump Out mentioned in yesterday’s update will not take place […]
Myles Standish Hall – Construction Activity – For 3/3/18 to 3/16/18:
For 3/3/18 to 3/9/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 3/3/18
Saturday Work – 3/3/18 Clean up and loadout Staging removal – Beacon Street and Point Park
Goldman School of Dental Medicine – Construction Update – 2/23/18
This notification comes to you as we have reached a milestone in the addition and renovation project at the Henry […]