Category: Alerts
Goldman School of Dental Medicine – Construction Update – 4/26/19
During the weekend of April 27 Due to last weekend’s weather, the closure of East Newton Street to perform the […]
BU Children’s Center – Construction Update – 4/26/19
During the week of April 29th ACM abatement The abatement team will finish their work in the first zone of […]
Geothermal Well Drilling Initiative – Construction Update – 4/26/19
During the week of April 29th Park Test Well #3 Driller has reached a total depth of 1390’ and is […]
Goldman School of Dental Medicine – Construction Update – 4/19/19
During the weekend of April 20th • Crews will be working Saturday to continue making final connections for the structural […]
Geothermal Well Drilling Initiative – Construction Update – 4/19/19
During the week of April 22nd Park Test Well #3 Laframboise to continue to mud rotary drill with the PDC […]
Geothermal Well Drilling Initiative – Construction Update – 4/12/19
During the week of April 15th Park Test Well #3 Driller has averaged approximately 100 ft. per day for a […]
BU Children’s Center – Construction Update – 4/12/19
During the week of April 15: Construction and renovation activities kick off with efforts to make-safe existing utilities and services. […]
Goldman School of Dental Medicine – Construction Update – 4/12/19
During the weekend of April 13: The City of Boston has issued a permit allowing GSDM to temporarily close East […]
Goldman School of Dental Medicine – Construction Update – 4/5/19
During the weekend of April 6: Crews will be working Saturday to continue making final connections for the structural steel […]
Geothermal Well Drilling Initiative – Construction Update – 4/5/19
During the week of April 8: Park Test Well #3 Driller received a delivery of new drill rod on 4/1 […]