Category: Alerts
Geothermal Well Drilling Initiative – Construction Update – 1/24/20
During the week of January 27th Parking Lot N The drilling subcontractor will continue installing the high-performance geothermal exchange vertical […]
Goldman School of Dental Medicine – Construction Update – 1/24/20
During the weekend of January 25: On Saturday, work will continue throughout the interior of the seven-story west addition, with […]
Goldman School of Dental Medicine – Construction Update – 1/17/20
A milestone: This is GSDM’s 100th Project Update! During the weekend of January 18: On Saturday, work will continue throughout […]
CFA Renovations – Construction Update – 1/17/20
During January 17th – January 24th: (Please note that there is work scheduled for Saturday, January 18th and Sunday, January […]
Geothermal Well Drilling Initiative – Construction Update – 1/17/20
During the week of January 20th Parking Lot N The drilling subcontractor will continue installing the high-performance geothermal exchange vertical […]
BU Children’s Center – Construction Update – 1/16/20
During the week of January 13th On site, work includes excavating for and installing the stormwater infiltration system. Main Building […]
Geothermal Well Drilling Initiative – Construction Update – 1/10/20
Parking Lot N Installation of high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of […]
CFA Renovations – Construction Update – 1/10/20
During January 10th – January 17th: (Please note that there is work scheduled for Saturday, January 11th and Sunday, January […]
Goldman School of Dental Medicine – Construction Update – 1/10/20
During the weekend of January 11: On Saturday, work will continue throughout the interior of the seven-story west addition, with […]
Geothermal Well Drilling Initiative – Construction Update – 1/6/20
Parking Lot N The drilling subcontractor will be installing the high-performance geothermal exchange vertical piping within the completed boreholes in […]