Category: Alerts
Center for Computing & Data Sciences – Construction Update – 07/01/22
During the weekend of July 2nd On Saturday, crews will continue working from the elevated platforms to construct the 15th […]
Kilachand Hall Phase 2 – Construction Update – 07/01/22
Saturday, July 2nd Work hours are 7 am – 3:30 pm. BrandSafway will continue with scaffold erection along the west […]
Kilachand Hall Phase 2 – Construction Update – 06/24/22
Saturday, June 25th Work hours are 7 am – 3:30 pm. Now that the fire escape has been removed, BrandSafway […]
Center for Computing & Data Sciences – Construction Update – 06/24/22
During the weekend of June 25th On Saturday, crews will continue working from the elevated platforms to construct the 15th […]
Kilachand Hall Phase 2 – Construction Update – 06/17/22
Saturday, June 18th Work hours are 7 am – 3:30 pm BrandSafway will have 12-15 crew members on site erecting […]
Center for Computing & Data Sciences – Construction Update – 06/17/22
During the weekend of June 18th On Saturday, crews will continue working from the elevated platforms to construct the 15th-floor […]
Kilachand Hall Phase 2 – Construction Update – 06/10/22
Saturday, June 11th Work hours are 7 am – 3:30 pm BrandSafway will have 12 men onsite erecting scaffolding along […]
Center for Computing & Data Sciences – Construction Update – 06/10/22
During the weekend of June 11th On Saturday, installation of the atrium’s monumental stair and communicating tower stair will continue. […]
Kilachand Hall Phase 2 – Construction Update – 06/03/22
During the week of June 6th The traffic management plan for the project is still being finalized with the City […]
Center for Computing & Data Sciences – Construction Update – 06/03/22
During the weekend of June 3rd On Saturday, installation of the atrium’s monumental stair and communicating tower stair will continue. […]