Author: Lauren Alzate
Fire Alarm Inspection 2/18/2013 – 2/22/2013
2/18/2013 Testing from 7am – 3pm 141, 143, 145, 147, 232, 236 Bay State Rd. 2/19/2013 Testing all rooms and […]
The Unsung Heroes Behind Nemo Cleanup
BU staff and students pulled double and triple shifts during the storm to keep operations running smoothly.
Fire Alarm Inspection 2/11/2013 – 2/15/2013
2/11/2013 Testing from 7am -3pm 648, 650, 654, 656 Beacon St. 533 – 541 Commonwealth Ave 2/12/2013 Testing all rooms […]
Admissions Reception Center – Construction Activity 2/4/13
We are now moving on into Part 2 of the Sewer Separation Project that will install new storm line drainage […]
Fire Alarm Testing 25 Buick Street 2/9/13
Boston Fire Department will be performing final acceptance testing of the fire alarm system at 25 Buick Street on Saturday […]
New Balance Field Construction Activity for the Period of February 4 – February 9
**The contractor will be working on Saturday, 2/9/2013, beginning at 8:00am** 1. Site Work: Already underway and continuing for the […]
Fire Alarm Inspection 2/4/2013 – 2/8/2013
2/4/2013 Testing all rooms and common area from 7am – 3pm 273, 275 Babcock St. 2/5/2013 Testing from 7am – […]
Three BU Restaurants Get Four Stars for Eco-Friendliness
Center for Student Services eateries earn high honors 01.28.2013 By Leslie Friday Sabrina Pashtan, Dining Services sustainability coordinator, applies a Certified […]
Fire Alarm Inspection 1/28/2013 – 2/1/2013
1/28/2013 Testing all rooms and common area from 7am – 3pm 512 Beacon st. Rooms only from 1st fl to […]
New Balance Field Construction Activity for the Period of January 28 – February 2
Anticipated construction activities for the week of January 28 – February 2: **The contractor will be working on Saturday, 2/2/2013, […]