Author: Lauren Alzate
New Balance Field Construction Activity for the Period of April 16 – April 20
Anticipated construction activities for the week of April 16 – April 20: *The contractor will not be working on Saturday, […]
Admissions Reception Center Construction 4/5/13
Other than some brick and concrete sidewalk replacement where we had been trenching in the Alpert Mall area, and final […]
New Balance Field Construction Activity for the Period of April 8 – April 12
Anticipated construction activities for the week of April 8 – April 12: **The contractor will be working on Saturday, 4/6/2013, […]
Engineering Product Innovation Center Construction Activity for the Period of April 8 – April 12
Anticipated construction activities for the week of April 8 – April 12: 1. Site Work – The contractor has completed […]
Mayor Signs Off on BU Master Plan
Way cleared for 10-year Charles River Campus makeover 04.05.2013 By Susan Seligson In the wake of recent approvals by the […]
Engineering Product Innovation Center Construction Activity for the Period of April 1 – April 5
Anticipated construction activities for the week of April 1 – April 5: 1. Site Work – The contractor will be […]
Fire Alarm Inspection 4/1/2013 – 4/5/2013
4/1/2013 Pre test 7am – 3pm 14 Buswell St. 4/2/2013 Testing all rooms and comm area from 7am – 3pm […]
Fire Alarm Inspection 3/25/2013 – 3/29/2013
3/25/2013 Pre-test 7am – 3pm 14 Buswell St. 3/26/2013 Pre-test 7am – 3pm 14 Buswell St. 3/27/2013 Testing all rooms […]
Engineering Product Innovation Center Construction Activity for the Period of March 25 – March 29
Anticipated construction activities for the week of March 25 – March 29: 1. Site Work – The existing concrete slab […]
New Balance Field Construction Activity for the Period of March 25 – March 29
Anticipated construction activities for the week of March 25 – March 29: **The contractor will be working on Saturday, 3/23/2013, […]