CILSE – Construction Activity – Week of 5/16/16
On the Commonwealth Avenue side of the building, the team will continue replacing some of the glass units. Air and vapor barrier installation will continue on the Cummington Mall side, and installation of window frames will continue.
Myles Standish Hall – Construction Activity – Week of 5/16/16
Deliveries: Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.
Beacon Street Re-Striping: Our site subcontractor will be re-striping Beacon Street as required to make room for our Jersey barriers. (Per BTD this striping work will need to be done on off-hours.)
Myles Standish Hall – Construction Activity – Week of 5/8/16
Work taking place this week will not make any noise so as not to disturb the students during finals week. Work will begin at 7 a.m. and deliveries to the site will start at 8 a.m. All deliveries will enter the site through the Bay State Road entrance and will use one elevator to get stock to basement.
CILSE – Construction Activity – Week of 5/8/16
On the Commonwealth Avenue side of the building, the team will continue replacing some of the glass units. Air and vapor barrier installation will continue on the Cummington Mall side, as well as the installation of window frames. On the Morse Auditorium side, there will be framing and sheathing from the swing staging, and the team will begin the installation of the air and vapor barrier from the mast climber.
CILSE – Construction Activity – Week of 5/1/16
On the Commonwealth Avenue side of the building, the project team will be replacing some of the glass units starting next week. There will be welding for the exterior wall system on the College of Communications side.
Myles Standish Hall – Construction Activity – Week of 5/1/16
Work taking place this week will not make any noise so as not to disturb the students during finals week. Work will begin at 7 a.m. and deliveries to the site will start at 8 a.m.
Unsubscribe
Subscribe for Project Notifications
Contact the Project Team
CILSE – Construction Activity – Week of 4/24/16
Exterior curtain wall is substantially complete on the Commonwealth Avenue side of the building, with some minor adjustments required. Curtain wall installation on the College of Communications side will continue on the 8th floor. Air and vapor barrier installation will continue on the Cummington Mall side, as well as installation of window frames and welding clips for the curtain wall.