Center for Computing & Data Sciences – Construction Update – 1/15/21
During the weekend of January 16th Crews will be on site Saturday to continue to install rebar and formwork at […]
Goldman School of Dental Medicine – Construction Update – 1/15/21
During the weekend of January 16: A crew will take advantage of the weekend (when fewer trade workers are present […]
Goldman School of Dental Medicine – Construction Update – 1/8/21
During the weekend of January 9: On Saturday, January 9, a work crew will be removing demolition debris from the […]
Center for Computing & Data Sciences – Construction Update – 1/8/21
During the weekend of January 9th Crews will be on site Saturday to continue the installation of rebar and formwork […]
Center for Computing & Data Sciences – Construction Update – 12/23/20
During the week of December 28th Removal of the Support Of Excavation (SOE) bracing will continue in the tower and […]
Goldman School of Dental Medicine – Construction Update – 12/23/20
Special Note: The winter intersession for the Henry M. Goldman School of Dental Medicine begins at 5 p.m. on Wednesday, […]
Center for Computing & Data Sciences – Construction Update – 12/18/20
During the weekend of December 19th Workers will be on site Saturday to continue installing rebar at the core structure […]
Goldman School of Dental Medicine – Construction Update – 12/18/20
During the weekend of December 19: On Saturday, December 19, East Newton Street will be closed to vehicular traffic, while […]
Goldman School of Dental Medicine – Construction Update – 12/11/20
Special Note: On Wednesday, December 9, 2020, GSDM received approval from the Department of Public Health to begin patient care […]
Center for Computing & Data Sciences – Construction Update – 12/11/20
During the weekend of December 12th On Saturday, workers will be on site to continue installing rebar and formwork for […]