Kilachand Hall Phase 2 – Construction Update – 07/14/23
General Project Information Daily Work Hours from 6 am – 3 pm. (6 am for interior work) The Traffic Management Plan for […]
West Campus Dining Expansion – Construction Update – 07/14/23
General Project Updates This past week, excavation work on the new sidewalk was completed, and the site was prepped and […]
Kilachand Hall Phase 2 – Construction Update – 07/07/23
General Project Information Daily Work Hours from 6 am – 3 pm. (6 am for interior work per ISD permit) The Traffic […]
West Campus Dining Expansion – Construction Update – 07/07/23
General Project Updates This past week, exterior work began and excavation of the site’s utilities and stockpiling soil took place. Soffit […]
Kilachand Hall Phase 2 – Construction Update – 06/30/23
General Project Information Daily Work Hours from 6 am – 3 pm. (6 am for interior work per ISD permit) The Traffic […]
Kilachand Hall Phase 2 – Construction Update – 06/23/23
General Project Information Daily Work Hours from 6 am – 3 pm. ( 6 am for interior work per ISD permit) The […]
West Campus Dining Expansion – Construction Update – 06/23/23
General Project Updates Work is ongoing for the West Campus Dining Expansion and repairs to the West Campus steam line […]
Kilachand Hall Phase 2 – Construction Update – 06/09/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 6/9/23
General Project Updates Millwork was installed in the Residence Life spaces. In the dining hall, flooring was demolished, electrical wiring was […]
Kilachand Hall Phase 2 – Construction Update – 06/02/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]